Dyal WTP Closed Loop Transition

The project includes condition assessment of the existing electrical substation and switch gear and upgrading the switch gear to streamline the process of switching to and from backup power in case of an emergency.

Status Completed
Design Start October 2013
Design Completion April 2014
Construction Start December 2014
Construction Completion September 2017
Spent Budget $786,142
Total Budget $786,589
Percent Complete 100%