Fiske Boulevard Pipeline Improvements - Peachtree to Highland

This is a joint project between the City of Cocoa’s Utilities and Public Works Departments, consisting of the replacement of approximately 2,900 feet of asbestos cement water main with new PVC water main, including the installation of new fire hydrants and service lines.

Status On Hold
Design Start October 2017
Design Completion May 2021
Construction Start TBD
Construction Completion TBD
Spent Budget (Design) $26,258
Total Budget $887,137
Percent Construction Complete 0%

                                                                                                                                                                Statistics as of March 2023